10/28/24

Blue Print Columbus: North Linden 1 Construction Update - Week of October 14th

Blue Print Columbus

Please note that construction schedules are subject to change due to weather, site issues, etc. Reference this MAP to view the impacted construction areas for next week. Unsure about which is your area? Visit the Blueprint- map and type in your address to find out!
Check out the pre-construction meeting available on the Blueprint website.

LCP Cover.jpg

9/30/24

Construction Updates for Columbia Gas

Columbia Gas

Beulah Rd closure remains in effect. Limited access on Crestview Dr - Material (pipeline deliveries and welding) Impact with stringing of pipeline

LCP Cover.jpg

9/23/24

TRAFFIC ALERT: 71 / Hudson St

Starting Monday morning, Sept. 23, the northbound I-71 exit ramp to Hudson St will be open only to traffic using the ramp’s eastbound right turn lane. The through lane/left turn lane will be closed for construction for approximately 7 days and traffic detoured to the Weber Rd exit. Motorists should follow the posted detour and use Weber Rd to Indianola Ave to get back to Hudson St.

IMPORTANT ROAD CLOSURE NOTICE: Cleveland Ave at Myrtle Ave Project
Closure Area: Myrtle Ave, east of Cleveland Ave
Closure Dates: Starting early next week until approximately September 30
Reason for Closure: Installation of storm lines running from Cleveland Ave to the Linden Ave intersection
Traffic Impact: One lane of northbound traffic on Cleveland Ave will be maintained. Myrtle Ave will be fully closed to ensure safety during the construction.

LCP Cover.jpg

10/28/24

Gas Line Replacement

Columbia Gas

What is the Central Columbus NCHP Project? To comply with federal requirements, Columbia Gas of Ohio is replacing our gas lines within the Linden and Clintonville communities. There will be minimal direct impact to Columbia Gas customers. Pipeline construction may affect traffic throughout the duration of the project, as most work will be done in the road right-of-way. We ask all motorists to be patient and be respectful of all work zone directives.

LCP Cover.jpg

9/16/24

Map of Work Week of September 16th

Blueprint Columbus

Starting Monday morning, Sept. 23, the northbound I-71 exit ramp to Hudson St will be open only to traffic using the ramp’s eastbound right turn lane. The through lane/left turn lane will be closed for construction for approximately 7 days and traffic detoured to the Weber Rd exit. Motorists should follow the posted detour and use Weber Rd to Indianola Ave to get back to Hudson St.

Construction is improving the east leg of the Hudson St intersection at I-71 as part of the total reconstruction of Hudson St from I-71 to Cleveland Ave.

LCP Cover.jpg

8/30/24

IMPORTANT ROAD CLOSURE NOTICE: Cleveland Ave at Myrtle Ave Project

City of Columbus

Stay informed about upcoming changes in our neighborhood due to the ongoing Cleveland Ave at Myrtle Ave project. Starting early next week, the city will be making significant progress on the northeast corner of this project, which will necessitate a temporary road closure.

Key Details:
- Closure Area: Myrtle Ave, east of Cleveland Ave
- Closure Dates: Starting early next week, until approximately September 30
- Reason for Closure: Installation of storm lines running from Cleveland Ave to the Linden Ave intersection
- Traffic Impact: One lane of northbound traffic on Cleveland Ave will be maintained. Myrtle Ave will be fully closed to ensure safety during the construction.

We understand that road closures can be inconvenient, and your patience is appreciated as the city works to improve our infrastructure. Please plan your travel routes accordingly and follow any posted detour signs to help navigate around the construction zone.